The anticipated timetable for the consideration and approval of the Masterplan and preparation and submission of outline planning application is set out below:

  • Draft Masterplan completed – January 2019
  • 6 week Consultation period – from mid-February 2019
  • Final revisions to Shepherd’s Grove Masterplan – End of March 2019 to End of April 2019
  • Final Masterplan Preparation – May 2019
  • Masterplan to Full Council for approval – July 2019
  • Report to St Edmundsbury BC (West Suffolk) Cabinet – August 2019
  • Screening/Scoping Request to Council for Environmental Impact Assessment – August
    2019
  • Adoption of Masterplan as Supplementary Planning Guidance – September 2019
  • Preparation of outline planning application and supporting documents – Autumn/Winter
    2019
  • Submission of outline planning application – Spring 2020
  • Approval of outline planning application – late Summer 2020
  • Approval of ‘reserved matters’ – Spring 2021
  • Start on site – Summer 2021.